| Item | Share (typical) | Basis |
|---|---|---|
| Board | 60-70% | Blank area x board price |
| Printing | 5-15% | Colours x quantity |
| Die cutting / slotting | 8-15% | Per unit, die cost separate |
| Gluing / stitching | 3-8% | Per unit |
| Packing and freight | 3-8% | Per batch or per cubic metre |
Two items are not proportional: waste (3-5%) and the one-off die (hundreds to thousands of CNY).
Board cost = blank area (m2) x board price (CNY/m2)
Blank area = (blank width + bleed/trim) x (blank height + bleed/trim) / 1,000,000
Critical: use the flat blank bounding area, not the finished surface area - quoting on finished dimensions understates by 30% or more.
| Step | Calculation | CNY |
|---|---|---|
| Blank area | (1.48+0.02) x (0.66+0.02) = 1.02 m2 | - |
| Board | 1.02 x 3.2 | 3.26 |
| Printing (1 colour) | - | 0.25 |
| Die cutting / slotting | - | 0.10 |
| Gluing | - | 0.06 |
| Packing / freight | - | 0.05 |
| Subtotal | - | 3.72 |
| Waste 4% | 3.72 x 4% | 0.15 |
| Cost | - | 3.87 |
| Margin 15% | - | 0.58 |
| Quote | - | 4.45 / pc |
Plus a one-off die of about CNY 400: CNY 0.40/pc at 1,000 pieces, thinner at higher volumes.
| Process | Basis | Reference at 1,000 pcs |
|---|---|---|
| 1-colour flexo | Per plate set | 0.15-0.30 / pc |
| 2-colour | Two sets, registration | 0.30-0.55 / pc |
| Die cutting | Machine time per 1,000 | 0.08-0.15 / pc |
| Slotting (inline) | With printing | included |
| Gluing | Per 1,000 | 0.04-0.10 / pc |
| Stitching | Per 1,000 | 0.08-0.15 / pc |
Larger runs cut process cost, not board cost: setup time (plate mounting, die fitting, gluer adjustment, 20-60 minutes each) gets spread thinner.
| Quantity | Process multiplier | Reference price (base 4.45) |
|---|---|---|
| 300 | 1.6-2.0 | 5.6-6.2 |
| 1,000 | 1.0 | 4.45 |
| 5,000 | 0.8 | about 4.1 |
| 10,000 | 0.7 | about 3.9 |
Forgetting waste (3-5%) - the job loses money on completion. Quoting on finished dimensions instead of blank area - underestimates by 30%+. Omitting the validity period - a 5% board rise in a week turns a signed order into a loss.
For accurate blank area, generate the dieline from internal dimensions and read the blank size directly; the built-in quote panel then fills material and process rates automatically.